History

Sagrada Família Construction Timeline

From the first stone in 1882 to the central tower completion — 140 years of building, setbacks, and breakthroughs. The full chronological story.

TL;DR

Construction began in 1882, stalled after Gaudí's death in 1926, was severely set back by the Civil War in 1936, resumed slowly through the mid-20th century, and has accelerated dramatically since the 1990s. Computer-aided design has transformed what's possible. More has been built since 2000 than in the first 80 years combined. The building is projected to be substantially complete around 2026–2030.

1882–1925 The Gaudí Years

Crypt completed (1889). Apse completed (1893). Nativity façade largely complete. Gaudí devotes himself entirely to the project from 1914.

1926–1935 After Gaudí

Work continues under architect Domènec Sugrañes using Gaudí's surviving models. Nativity façade towers progressed. The project struggles for funding.

1936 Civil War Destruction

Anarchist militia burns the crypt, destroys Gaudí's studio and workshop, and sets fire to his plaster models. Much of his original documentation is lost. Construction halts.

1940–1970 Slow Reconstruction

Architects painstakingly reconstruct Gaudí's vision from photographs, surviving fragments, and geometric principles. Construction resumes but proceeds extremely slowly.

1970–2000 Acceleration Begins

Computer modelling validates and extends Gaudí's geometric systems. The Passion façade is begun (1954) and Subirachs starts the sculptures (1986). Construction accelerates significantly.

2000–2020 Modern Era

UNESCO World Heritage Site designation (2005). Pope Benedict XVI consecrates the basilica (2010). The central nave is completed (2010). Tower construction accelerates. Cranes are a permanent fixture.

2020–2025 Final Phases

Tower of Jesus Christ begins (2021). Major tower completions. The Glory façade portal begins construction. The building in 2025 is more complete than at any previous point in history.

The Civil War and What Was Lost

The night of 20 July 1936 was the most damaging in the building's history. Anarchist militia attacked the crypt, burned Gaudí's workshop, and destroyed the plaster models he had spent decades perfecting. The workshop fire lasted several days. When it was over, roughly 70 percent of Gaudí's surviving design documentation had been lost.

What survived came from multiple sources: photographs taken during construction, geometric principles Gaudí had published and described in writing, fragments of plaster models recovered from the ruins, and the memory of architects who had worked directly with Gaudí. The painstaking reconstruction of his vision from these scraps took decades and is itself one of the great acts of architectural scholarship of the 20th century.

How Modern Technology Changed Everything

The shift from hand calculation to computer modelling in the 1980s and 1990s transformed what was possible. Gaudí's geometric systems, based on paraboloids, hyperboloids, and helicoidal surfaces, were perfectly suited to computational modelling. What had taken Gaudí years of physical experimentation with hanging chain models could now be validated and extended digitally in months.

The Barcelona-based architectural firm currently overseeing the building has used parametric design software to generate and verify every surface on the remaining towers. The result is construction that Gaudí would recognise as his own because it proceeds from his geometric principles, even where his specific drawings no longer exist.

Stone is now pre-cut off-site using CNC machines programmed from the digital models. Work that once required master stonecutters working by hand for months can now be completed in weeks. This is why more has been built since 2000 than in the previous eight decades combined.

Key Milestones at a Glance

Year Milestone
1882 First stone laid, 19 March
1883 Gaudí takes over as chief architect
1889 Crypt completed
1893 Apse completed
1926 Gaudí killed by tram; Nativity towers incomplete
1930 Nativity façade towers completed by collaborators
1936 Civil War fire destroys workshop and most plans
1954 Passion façade begun
1978 Passion façade towers completed
1986 Subirachs begins Passion façade sculptures
2000 School of Gaudí restoration completed
2005 UNESCO World Heritage Site designation
2010 Papal consecration by Benedict XVI; nave complete
2021 Virgin Mary tower completed; Jesus Christ tower begun
2026 Centenary of Gaudí death; Jesus Christ tower projected complete

See the Building Mid-Construction

Visit now and witness the most extraordinary building project in human history still being built.

Free cancellation Instant confirmation 4.8★ · 50k+ reviews

Related Guides

Construction Timeline FAQs

Click any question to reveal the answer.

How long has the Sagrada Família been under construction?

The Sagrada Família has been under continuous construction since the first stone was laid on 19 March 1882. As of 2025, that is over 143 years of building — making it the longest continuously active construction project in modern architecture. No other building project in history has taken as long to complete.

Why has it taken so long to build the Sagrada Família?

Several factors explain the extraordinary timeline. Gaudí's design is phenomenally complex, requiring solutions to structural problems that had never been attempted before. Funding comes entirely from visitor admission fees and private donations — no public money has ever been used. The 1936 Civil War destroyed Gaudí's original plans and studio, adding decades of reconstruction time. And the ambition of the project keeps expanding.

What has been built in the most recent years?

Since 2010, construction has been remarkably fast by the project's own standards. The central dome was completed and the Tower of Jesus Christ began rising in 2021. As of 2025, all six evangelist and apostle towers on the apse are substantially complete, and the Glory façade portal is under construction. More has been built in the last 20 years than in the previous 80.
From
€26 per person
Free cancellation
Check availability